Finland tells Google to stop building two data centers until it checks the environment

A Finnish regulator ordered Google to pause construction at two data center sites until environmental reviews are done, a month after the company pledged $15 billion for AI infrastructure there.

Google picked Finland for its biggest European bet, and Finland has now pressed pause. On Tuesday the country's licensing and supervision agency, known as LVV, told a Google subsidiary to stop building data centers at Muhos and Kajaani until environmental impact assessments are finished.

What happened

The order covers the heavy, hard-to-undo work: clearing trees and topsoil, digging, quarrying, crushing rock, moving soil, cutting ditches and building roads and storage areas. Lighter work that can easily be reversed, such as planning, measuring and soil surveys, may continue. Google has until October 23 to stop.

The agency's environment chief said these activities change the landscape in ways the assessment process is meant to study before anything happens. In other words, the review is supposed to come first, not after the bulldozers.

Google said it would follow the guidance and admitted it had fallen short of its own standards. It added that it had acted in good faith under Finland's Forestry Act, run nature surveys, and plans to plant trees across 130 hectares (about 320 acres) at Muhos.

Why it matters

The timing is awkward. Only a month ago Google committed $15 billion to AI infrastructure in Finland, its largest investment in Europe, to be spent through 2028 on data centers and related projects such as energy.

Finland has become a magnet for these projects because it has spare land and power, both scarce in most of Europe. Several projects of hundreds of megawatts each have been announced, earning it the nickname "Texas of Europe," after the US state that has drawn huge AI builds from Google, Meta, Microsoft and Anthropic.

For Alphabet, Google's parent, the money is small next to its size. Noorult's data from company filings shows about $244 billion of net income over the last twelve months and a stock-market value near $4.25 trillion as of October 7. The bigger signal is that local permits, not just chips and power, can slow the AI buildout.

What to watch

  • How long the environmental assessments at Muhos and Kajaani take.
  • Whether the pause pushes back any part of the 2028 spending plan.
  • Whether other data center projects in Finland face similar checks.

Alphabet's full financials are on its Noorult company page.

The companies in this story

Based on reporting by CNBC: Google ordered to halt work on two data centers in ‘Texas of Europe’. Facts, not advice.