25 September 2026
Oracle must keep paying for its giant New Mexico data center even if the power never arrives
Oracle has flagged a power-supply problem at Project Jupiter, a key site for its OpenAI deal, but its contract still makes it cover investors' interest and returns for up to three years.
A data center without electricity is just a very large, very expensive shed. That is the risk Oracle is carrying at "Project Jupiter", a 1,400-acre campus under construction in Doña Ana County, New Mexico, according to people familiar with the deal who spoke to the FT.
What happened
Project Jupiter is central to Oracle's $300 billion contract to supply computing power to OpenAI, the heart of Oracle's plan to become a major AI data center player. The site is being developed by a unit of Blue Owl Capital, with Oracle as the tenant. It has hit permitting delays amid growing local opposition, and Oracle has sent Blue Owl a force majeure notice about the power supply. Force majeure is a standard contract clause that can excuse a party when events outside its control make it impossible to deliver.
Here is the catch. Under the contract, if the first phase is not ready by its deadline in the first half of 2027, Oracle still has to pay a "carry cost" instead of rent for up to three years. That payment covers the full interest owed to lenders plus a set return for Blue Owl's investors. In other words, the power risk sits with Oracle, not the people who financed the project. There is also some disagreement over whether force majeure can even be triggered before the scheduled completion date.
Oracle said the notices do not mean a delay and that the project remains on schedule. Blue Owl said the notice does not change the financial commitments.
Why it matters
The money involved is large. More than 20 banks, led by BNP Paribas, Goldman Sachs, MUFG and SMBC, lent $18 billion of construction debt for the project late last year. The plan was to sell much of that debt on to other investors, but those efforts stalled on worries about Oracle's creditworthiness after a record borrowing spree, leaving the banks holding more than they wanted.
Those loans have since traded below 90 cents on the dollar, meaning buyers would only pay about 90% of face value or less, a sign that lenders see more risk than when the deal was signed. The four-year loan pays 2.5 percentage points above SOFR, a benchmark short-term interest rate.
For investors, this is a window into the hidden costs of the AI build-out. Contracts measured in hundreds of billions of dollars depend on something as basic as getting a local power hook-up approved on time.
What to watch
- Whether the power permits for Project Jupiter are granted before the 2027 deadline.
- The trading price of the project's loans as a real-time gauge of lender nerves.
- Any update from Oracle on the site in its next earnings report.
The companies in this story
Based on reporting by the Financial Times: Oracle on the hook to pay data centre investors even if site has no electricity. Facts, not advice.
More news
- Anthropic's IPO, in numbers: 825 million shares at $70 to $78, and a $1.4 trillion price tag
- Trump says the Nvidia scandal didn't endanger US security, and stands by Lutnick
- Nvidia's first earnings without Huang: what Kress will be asked on Tuesday
- Buffett gives away $5.5 billion of Berkshire stock in his Thanksgiving letter
- Banks are using AI to trim back offices. Proof that it adds revenue is harder to find
- IMF chief says the world economy leans too hard on AI as circular deals top $1 trillion